Water and grid questions dominate first public session on EverWind's AI data centre
Officials from Nova Scotia, Richmond County and EverWind Fuels answered public questions Tuesday at the first of three information sessions on EverWind's proposed $8-billion AI data centre in Point Tupper. The streamed session was announced less than 10 hours ahead. Warden Lois Landry said a water contingency plan would curtail industrial users, including the data centre, during drought, while Port Hawkesbury water customers keep priority. Deputy energy minister Stephen MacDonald said EverWind has agreed to bear the incremental costs of its grid connection, and grid operators concluded the system can handle the extra load. EverWind estimates over 2,000 construction jobs.